Distractions

This section is devoted to all those NON radio projects that distracted Don from his hobby....  ;-) 
(text follows these pics)

Zone Valve Manifold

All copper with unions to make valve replacement easy.

Zone Valves

with useless plastic manifold, unserviceable

Manifold and zone valves

ready to install

A pit in front border

ready for the zone valve box.... note black water feed pipe and white storm drain pipe

Zone Valve Box

with feed pipe, manifold and three zone valves. Zone 1 on left, 2 in middle, 3 on right

Zone Valve Box

with zone 1 and 2 piping to front yard. Zone 3 will be added, in Trench 5a,b,c going down south side of house and part of rear lawn.

Trench 1 & 2

Trench 1 cuts off to the right across top of lawn, to driveway area. Trench 2 follows south lawn edge.

Trench 2

front south trench

Trench 3

on south side of driveway

Trench 4

on north side of driveway, note black feed pipe sticking out of "trench" through driveway... made by removing the 2x6 slab spacer

At the well head

white pipe at left is from well head. Black pipes are distribution to yard and also the north and south ends of house. Lots of plumbing to be done here.

Turf Truck

arrived 7 AM 8jun05

Forklift Dismount

off rear of trailer

Turf Unload

too easy

Turf on drive

now the easy work starts! All the prep was the hard part.

Half done lawn

but letting that pallet load of rolled turf sit for an extra day caused yellowing and a slower "take" once it was down.

Ross & Don

picnic on island, June05

Well Manifold 2

L to R: 2" plastic pipe to well head. copper feed to rear of lot. copper feed to south front. pottable water from house c/w valve and check valve. copper feed to north of lot. shut-off valve to pump. pump. pressure tank

Well Manifold 3

19jun05 side view. potable water can now go to auto sprinkler system in front yard. Next is to hook up well pump so we use well water on our lawns. Done by month end.

Wellhead

checking for a leak in the white PVC pipe. There was none.

Inside The Well Chamber

White pipe should NOT drop down as it does here. Fix it by hammering well pipe 7" down and reconnect with pipe running level.

Test

Determining that air leak is caused by setting well pipe too shallow.

Adding Extension

Five feet to pound down with sledge hammer.

4 hours later

As far as I can go before doing something to transfer hammering point higher up.

Rock Drill Rod

Wooden holder keeps drill rod aligned on top of pipe. Pound here.

2" Pipe Couplings

Smaller regular coupling on left was used to connect the five foot extension. It leaked after the above hammering. We now lift pipe up, replace with heavier "hammering coupling" on right.

Now Lift

Damaged coupling means pull it up, repair threads and replace coupling. Made a 16 foot, double 2x10 lifting beam. Hydraulic jack is at right end, where well pipe is, also.

Chain

...getting a grip on the pipe... 18july05

Half Way Up

Damaged extension is now half way out of the ground. Note left hand on handle of hydraulic car jack.

Finally Lifted

Damaged coupling and extension ready for replacement. Note the small inappropriate coupling.

Don's Pipe Yoga

Proper hammering coupling installed with big wrenches to get it TIGHT. Used 2-part epoxy with 8 hour open time on threads so it sets and seals after pounding down.

Tripod Assembly

Done in two stages. Next stage I use a ladder to get up and spike together the third leg and add pulley and rigging.

Tripod Done

Now add the new pipe extension and the 100 pound steel well pipe pounder.

All Set

New five foot extension with cheaper "protective" coupling at top and pounder above coupling.

Looking Up

Notice the finger blisters!

Well Head Almost There

Next step attach the "T" and check valve then couple to the PVC pipe leading to pump.

C'est Fini

21july05 closed up the well head in the early morning.. and off to Magna Bay on Shuswap Lake.

Engine No Head

26dec2005. Note milky mix of antifreeze and oil on 3 piston.

Cylinder Head

Top view.

Cylinder Head

Bottom view. Crack beside #3 intake valve can't be seen in this photo.

Engine Parts

On work bench.

Engine parts

A closer look. See notes below.

Hitachi SL2000 Print Engine

March2006, am currently working on this repair job

Roof Repairs-1

Leaky after 18 years. 12 hours to replace rotten decking & several bad shingles

Roof Repairs-2

ain't purdy but will keep out rain water til next year's new roof

RegsReno-1

Back of Reg's house

RegsReno-2

Siding Off

Notice flying critters

RegsReno-3

Yes those are honey bees in the mansard roof above my head. No stings happened, so far.

RegsReno-4

Inside wall before.

RegsReno-5

Window In, Day Two

RegsReno-6

Day Two. Olivia enjoying the view.

RegsReno-7

Day Three. Recessed book nook replaces old small window.

RegsReno-8

Day four. First mud coat, sanded

RegsReno-9

Day five. Siding back on.

Barb's Reno 1

Replacing rotten decking at Barb's Shuswap Lake home.

Barb's Reno 2

The demolition tools

Barb's Reno 3

Rot where wood was.

Barb's Reno 4

Finito.... and now for a coffee at a balcony table with a view of the lake. (see table/chairs in Small Wood Radios - Brand & Millen DR-102U)

Coffee Break

Shuswap Lake, early October

Laundry-1

Early November06. Upstairs toilet leak ruined laundry room gyproc ceiling. So started our remodeling. Dryer vent relocated.

Laundry-2

Washer, dryer, wash tub wall opened up, cut up. From this point re-construction begins.

Laundry-3

Redo tin pipe on dryer vent so it fits 4 inch hole from hole saw. Notice seam is soldered now and pipe is tapered.

Laundry-4

New drain to new washer box. Hot and cold water lines in. Dryer power box in. Messing with bottom of heat duct to get wash tub drain in.

Laundry-5

Decided to raise duct and heat vent. Opened up other side of laundry room wall for access.

Laundry-6

Finicky job getting gyproc cut so it simply flips upside down and voila.... heat vent is 8 inches higher after doing the tin work.

Laundry-7

... now sink drain is all in wall, so washer can go tight to wall.

Laundry-8

lower left dryer duct sticks out of wall by 1/2"... tappered firring strips added so gyproc can cover. Just shower P-Trap to raise 2" to allow higher ceiling.

Laundry-9

mechanical all done.

Laundry-10

other side sealed up.

Laundry-11

boarded, mudded, painted. Next is T-Bar ceiling, baseboards, window trim, cupboards.

Laundry-12

new cupboards sans handles

Laundry-13

the new sink stand and sink 10dec06

ControllerJob-1

I was given this and asked to make 6 more. It is a temperature controller.

ControllerJob-2

yellow wire goes to a thermocouple. Heating device plugs into back.

ControllerJob-3

Little black box is controller, programmed from front and has display.

ControllerJob-4

Custom made fiberglass reinforced black stand-off rings for controller's better fit in shallow box.

ControllerJob-5

Stand-off rings slip onto controller from the rear.

ControllerJob-6

Six new controllers. Two boxes with two. Two boxes with one.

ControllerJob-7

The boxes with two are 110vac outputs. Boxes with one are 220vac outputs.

ControllerJob-8

Symetry in design.... for future. Price?.... Not cheap. Perfect?.... close. Fun?... yes. Application?.... ;-)

Office Trash

180 pounds in 5 bags. Accumulated bookkeeping and client papers since 1989. Took 5 days of sifting and tossing out, to fill these bags in January '07.

Attic 1

Start of 80' attic catwalk. Looking West from ceiling trap door.

Attic 2

Half way along the "railway" track. West gable end in the distance.

Attic 3

2 by 8 reinforcing added under truss' 2 by 4 top stringer.

Attic 4

Same on the right. Note 2 by 6 cat walk decking.

Attic 5

All 2x8's in place. Glued and screwed to inside of OSB sheathing.

Attic 6

Now add 3/4" plywood. Glued and screwed

Attic 7

Reinforcing finished at top.

Attic 8

...and down the sides. Ready to start gable work outside.

Gable

Day 1.... 21mar07. 18 days of rain off and on. Gable as it was since 1987.

Gable

Day 1. Starting with the scaffold.

Gable

Day 2. 22mar. Finish bracing & decking scaffold. (now for the rotten barge boards)

Gable

Day 2. Sheet metal removed exposing rotten barge board.

Gable

Day 2. Removing the barge boards.... and two trips for lumber today.

Gable

Day 3. Rain all day. Loosen left eave trough. Remove right trough, aluminum soffit covers and two 2x4 facia rafters

Gable

Day 3 & 4. Work indoors: 4" of rain in last 12 hours. Build "dump truck box & bed.

Gable

Day 4. 24mar. 21 days of rain. Remove gutter for use at front of house.

Gable

Day 4. Gutter suspended from eye bolts using twine and counter-weights.

Gable

Day 4. Weight and counter-weight meet half way. With gutters gone we now can start gable extension work.

Gable

Day 4. Today's 4 inches of rain too much for old roof. Plastic stopped leak.

Gable

Day 5. 25mar. The focus of today's effort was to install this 4x4 and extend the 2x4 facia behind it.

Gable

Day 5. Upshot of 4x4. Also the "dump truck" on the car's roof rack. Tomorrow the right side of roof is stripped 5 feet back.

Gable

Day 5. "Dump truck" is 1/4 filled with shingles.

Gable

Day 6. 26mar07. Last of shingles stripped off. Ready for trip to dump.

Gable

Day 6. Ready to unload. Note the stupidly concieved "safety" bars making an easy job hard. Boneheads.

Gable

Day 6. Unload :-)

Gable

Day6. With help from my swamper, Herbert.

Gable

Day 6. End of the day.Two more supports installed. Toughest part is done.

Gable

Day 6. Finished with the dump truck.

Gable

Day 7. 27mar07. Today's challenge, install all the cantilevers.

Gable

Day 7. ... the wisdom of prebuilding the "catwalk" is evident.

Gable

Day 7. Quad erat demonstrandum. Next.... add the facias and new sheathing.

Gable

Day 8. 28mar07. Left side decked and tar papered. Now the platform becomes roof decking.

Gable

Day 8. Right side partly decked.

Gable

This is about as romantic as this job gets.

Gable

Day 9. 29mar07. The last of the sheathing. Slow day only 4 hours on job.

Gable

Day 10. 30mar07. Barge boards on. Carpentry done. 30 pound felt on, covered in plastic. Ready for new shingles.

Gable

Day 11. 1apr07. Barge boards have sheet metal covers. Also attached midline supports for soffit covers.

Gable

Days 12+13. 2,3apr07. Cutting aluminum soffit covers.

Gable

Day 12,13. Installing aluminum soffit covers. Taking down scaffold.

Gable

Day 13. Almost done with 32" overhang.